Project Timescales

Author

Tim Pizey

Status

Date

15/09/1999 18:44

Message

The project is estimated to take 80 hours, of which
10 are project management and the rest is currently allocated to ColinR.
Colin can only squeeze a few hours a week from his full time job.
Because of the Xmas period he may be able to do more, but
in theory the project might not be accomplished until April, which
I imagine is not acceptable.
TimJ has proposed that ColinR become the 'Art Director',
providing graphics and styling but farming out the
gif animation and page construction to JustineE or ANO.
To sort this out we need
- When the customer is expecting delivery (SimonT)
- Commitment to specific number of hours per fortnight (ColinR)
If we need to break the task down then ColinR should supply the
breakdown (ColiR).

grolier Project Board

 

Post Follow-up

Search This Board

 

Message Context:

Project Timescales Tim Pizey 15/09/1999 18:44

    Re: Project Timescales Colin Rainsforth 15/09/1999 18:44

        Re: Project Timescales Simon Tucker 15/09/1999 18:44

            Re: Project Timescales Tim Pizey 15/09/1999 18:44

                Re: Project Timescales Tim Pizey 15/09/1999 18:44

                    Re: Project Timescales Tim Pizey 15/09/1999 18:44

                        Re: Project Timescales Colin Rainsforth 15/09/1999 18:44



Home -  News -  Reference Sites -  Members -  Partners -  Guidelines -  Philosophy -  Your Details -  Logout