Message |
Colin alone cannot achieve this time scale. Colin can work 10 hours per week, which gives us seven weeks elapsed time. This means that the project will be delivered by 3rd week in February, allowing for some slippage the delivery date will be 01/03/98; which is brought forward by a month from the delivery date given with the estimate. To bring this time scale forward dramatically we will have to double up on personnel, which will increase costs. Please email me on how you wish to acheive the new timescales.
|