Message |
>Can you please explain why there will be additional costs for additional >personnel. > Simply because the job was estimated upon the assumption that Colin could do the work alone. If he has to divide the work into packages and then tie the packages together, to say nothing of breifing and monitoring whoever does the work, then it will take more time. I don't actually think that there is a way to introduce additional personnel and reduce the elapsed time that the job takes, as we are in a 'mythical man month' scenario. The only way to make this deadline is to work harder. I have talked with Colin and he has agreed to work over the holiday to ensure that we have reached the end of Phase 2 by 'the end of the third week in Jan'.
|