I have costed the various parts of the Iglu web site independently
of TimJ, using broad categories of work. My costings are as follows:
<pre>
Skeleton site - 3 weeks
Chalet (Search, list, details, shortlist, admin) - 2.5 weeks
Resort ( --"-- ) - 2.5 weeks
Ski Domain (list, details, admin) - 1 weeks
Bookings (add requirement, response,
confirmation, travel pack) - 3 weeks
Fixed Content (ski area/fitness, help, terms - 1 weeks
and conditions, insurance)
Administration (users, bargins, telephone, - 2 weeks
mailing list)
Calendar/Weather - 0.5 weeks
Others (e-mail, javascript, image upload) - 1.5 weeks
------------
680 hours
</pre>
TimJ's roughly comparable estimates are (roughly):
<pre>
Skeleton site (homepage + design) - 1 week
Chalet - 1.5 weeks
Resort - 1 week
Ski Domain - 0.5 weeks
Bookings - 2 weeks
Fixed content - 1.5 weeks
Administration - 3 weeks
Bulletin Board - 1 week
Calendar/Weather - 0.5 weeks
Others - 0.5 weeks
(Rounding errors) - 1.5 weeks
-----------
560 hours
</pre>
So, my estimate is 120 hours (3 weeks) over Tims, which is mainly
due to me setting aside 3 weeks rather than 1 for skeleton/graphic
design, and me thinking that handling Chalets and Resorts would
take more time than Tim.
We differ on the estimates of Bookings and Administration (but they
balance out, and Tim's probably right) and I think that the bulletin
board will take longer than Tim does. Tim has gone into more detail
about the misc. stuff at the bottom than I have, and so has a larger
figure.
Regards,
Myles

iglu Project Board

 

Post Follow-up

Search This Board

 

Message Context:

Iglu costings Myles Chippendale 21/09/1999 10:31

    Re: Iglu costings Myles Chippendale 21/09/1999 10:31

        Re: Iglu costings Tim Joyce 21/09/1999 10:31



Home -  News -  Reference Sites -  Members -  Partners -  Guidelines -  Philosophy -  Your Details -  Logout