Re: Project Timescales

Author

Tim Pizey

Status

Date

15/09/1999 18:44

Message

>Can you please explain why there will be additional costs for additional
>personnel.
>
Simply because the job was estimated upon the assumption that Colin could do the work alone. If he has to divide the work into packages and then tie the packages together, to say nothing of breifing and monitoring whoever does the work,
then it will take more time.
I don't actually think that there is a way to introduce additional personnel and reduce the elapsed time that the job takes, as we are in a 'mythical man month' scenario.
The only way to make this deadline is to work harder.
I have talked with Colin and he has agreed to work over the holiday to ensure that we have reached the end of Phase 2 by 'the end of the third week in Jan'.

grolier Project Board

 

Post Follow-up

Search This Board

 

Message Context:

Project Timescales Tim Pizey 15/09/1999 18:44

    Re: Project Timescales Colin Rainsforth 15/09/1999 18:44

        Re: Project Timescales Simon Tucker 15/09/1999 18:44

            Re: Project Timescales Tim Pizey 15/09/1999 18:44

                Re: Project Timescales Tim Pizey 15/09/1999 18:44

                    Re: Project Timescales Tim Pizey 15/09/1999 18:44

                        Re: Project Timescales Colin Rainsforth 15/09/1999 18:44



Home -  News -  Reference Sites -  Members -  Partners -  Guidelines -  Philosophy -  Your Details -  Logout